PROJECT IMPLEMENTATION

• Arial Topographical View Report
• Survey Drawing by the Company
• Peso -1 Clearance
• Soil Testing by Company Approved Consultant
• Environment Department’s Clearance
• Peso-2 Clearance
• Advertisement in Newspaper for Any One Having Interest in the Land Other Than the Owner
• NOC of the Fire Department
• Clearance by Irrigation Department
• Clearance by Electricity Board
• Clearance of Local Municipal Office
• Clearance by Public Works Department
• Clearance of Drawings for Installation of Equipments
• Civil Construction to Begin
• Peso-3 Clearance
• Payment of Security Amount for Equipment Installation
• Clearance of Chief Controller of Explosives > Sales Security
• Clearance of Weights & Measurement Department
• Clearance by State Highway
• Clearance of NHAI.
• Clearance of D C Office
• Clearance of Traffic Police
• Clearance of District Town Planner Office

• Route Survey
• Obtaining Statutory Clearances / Approvals & Land Acquisition
• Finalization of Land Restoration Charge for Pipe Line Laying
• Basic & Detailed Engineering
• Procurement of Compressors & Other Free Issue Items
• Award of Works Contract for CNG Stations
• Construction of Boundary Wall, Building, Canopy, Etc
• Dispenser Erection
• Compressor Erection
• Nloading Platform Erection
• Ascade Erection
• Electrical Works
• Commissioning